Archdesk Changelog logo

Changelog

Subscribe to Updates

Labels

  • All Posts
  • Fix
  • Announcement
  • Improvement

Jump to Month

  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • January 2025
  • December 2024
  • November 2024
  • October 2024
  • September 2024
  • August 2024
  • July 2024
  • May 2024
  • March 2024
  • February 2024
  • December 2023
  • October 2023
  • July 2023
  • April 2023
  • February 2023
  • December 2022
  • November 2022
  • October 2022
  • August 2022
  • July 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • September 2021
  • June 2021
  • May 2021
  • April 2021
  • March 2021
  • January 2021
  • December 2020
  • October 2020
  • July 2020
  • May 2020
  • February 2020
  • January 2020
  • December 2019
  • October 2019
  • September 2019
  • August 2019
  • June 2019
  • December 2018
  • November 2018
  • October 2018
  • September 2018
Changelog byAnnounceKit

Create yours, for free!

Announcement
8 months ago

Scheduling tasks updates

We added a couple of improvements for scheduling tasks that allow for more automation and flexibility when working on the project programme. Thanks to that, we are competitive in the market with a robust Scheduling module.

Auto-scheduling

In a previous release, we introduced automatic task scheduling for the Project Programme

Now, we’ve made it even better. Handling conflicts between dependencies and constraints is simpler. For example, if the task “Structural steel beams” is supposed to start on 10/10/2024 but is delayed because the “Concrete foundation” task isn’t finished, you’ll see a prompt with options to resolve the issue. You can either adjust the constraint or remove the dependency, giving you more control and flexibility in managing your schedule.

Project Start date

The Project Start Date is a fixed value that determines the timeline for all tasks. When you modify the Project Start Date, all task dates adjust automatically, making it easier to manage changes and maintain automatic constraints. 


Additionally, you can enable Project lines on the Gantt preview by going to Settings → Project Lines. This will display both the defined Project Start Date and the Project End Date, which is calculated as the end date of the last programme task. 

Critical path

Every task is important, but only some of them are critical. The critical path is a chain of linked tasks directly affecting the project’s finish date. If any task on the critical path is late, the whole project is late.